03 December 2009 Build Progress Update:
Despite the constant rain we've been having over the last few
weeks Clachan Construction are are still making great progress
with the skatepark build. Much of the flat bottom and coping is
now in place for the transitioned section making the teardrop
and beginnings of the hipped miniramp easy to see. Features are
also being added to the street section with the stepped manual
pad and some of the grind ledges in place. The next couple of
weeks will see a start on the over-vert corner block work and
placement of the coping so check back soon to see more build progress
updates as it moves forward...

 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
All The Build Photo Updates:
22 April 2010 Build Photos >
14 April 2010 Build Photos >
19 March 2010 Build Photos >
14 March 2010 Build Photos >
05 March 2010 Build Photos >
18 February 2010 Build Photos >
28 January 2010 Build Photos >
22 January 2010 Build Photos >
15 December 2009 Build Photos >
03 December 2009 Build Photos >
15 November 2009 Build Photos >
04 September 2009 Build Photos >
|
The Skatepark Layout:

The final layout for the Saughton Park
site was developed by the skaters and riders in the ESP group
in conjunction with architects Urban Design Futures and Dave Sowerby
acting to produce the layout plans. The skatepark layout covers
approximately 2100 square meters and features a mix of bowl and
street features to cater for all skill levels.
View the skatepark design >
|